‘Challenging and expensive’ – report casts doubt on Scotland’s plans for ubiquitous superfast broadband

Written by Margaret Taylor on 18 March 2022 in News
News

Auditor’s report finds difficulties are likely to persist in the Highlands and Islands

Credit: Mohamed Hassan/PxHere 

The Scottish Government is still some way off being able to provide “100% superfast broadband for all”, with over 100,000 properties in remoter parts of the country continuing to miss out.

In a progress report on the government’s R100 (Reaching 100%) programme, the Auditor General for Scotland, Stephen Boyle, noted that as the 107,000 homes and businesses that are still to be connected are in “the hardest to reach locations” completing the programme is going to prove “challenging and expensive”.

"The pandemic has shown that a fast and reliable broadband connection is an essential utility, but there is still work to do to connect or upgrade around 100,000 homes and businesses as part of the Scottish Government's plans,” Boyle said. "Infrastructure work, particularly in the Highlands and Islands will continue for a number of years. These are properties in the hardest to reach locations with difficult terrain, making it a huge challenge for government and its partners."

Work to connect properties in the north of the country has been hampered due to the geography of the region, although Boyle said a legal dispute over the contract for the work also held things up. That dispute was settled in 2020 and the contract was awarded to BT, which also won the contracts for the south and central regions. Following the delay, the number of premises that will be covered by the north contract had to be reassessed, meaning work did not get under way until August 2021.


Related content


The full rollout is not expected to complete until 2027. The initial plan had been to achieve full coverage by the end of 2021.

Liberal Democrat culture, media and sport spokesperson Jamie Stone, who represents Caithness, Sutherland and Easter Ross in the House of Commons, said his constituents are "fed up with being lumbered with stone-age broadband connections”, adding that both governments need to step up their efforts to serve citizens in remote parts of the country.

"The SNP promised to deliver access to high-speed broadband to every household and business in Scotland by 2021. That promise was junked at the first opportunity,” he said. "A reliable internet connection is an essential part of modern life. It has a major part to play in everything from education to starting a business. Both of our governments need to stop treating the far north as an afterthought."

Scottish Labour's rural spokesperson Colin Smyth added that the Audit Scotland report is "another slap-down" to the R100 programme.

“After years of delays and excuses, the programme is still struggling to deliver what was promised," he said. “The last two years have shown that reliable connectivity is a necessity, not a luxury, but for Scotland’s forgotten rural communities it’s been a case of super slow, not superfast broadband rollout. As everything from work to services to education moves online, more than ever the Scottish Government needs to up its game and stop leaving people behind."

 

About the author

Margaret Taylor is a journalist at PublicTechnology sister publication Holyrood, where this story first appeared. She tweets as @MagsTaylorish.

Share this page

Tags

Categories

CONTRIBUTIONS FROM READERS

Please login to post a comment or register for a free account.

Related Articles

Government creates Smart Data Council to target citizens’ monthly bills
18 April 2023

Numerous departments and industry groups to take part in initiative aiming to eliminate £1,000-a-year ‘loyalty penalty’

Cost of developing emergency alerts system pegged at £25m
5 June 2023

Minister reveals up more than £4m spent on testing, security and other support contracts

Ministry of Justice floats £200m opportunity for long-term WAN provider
1 June 2023

Department seeks bids for seven-year contract as part of major programme to replace networks

‘Extremely concerned and disappointed’ – more councils caught up in Capita breach
24 May 2023

Authorities have complained about the lack of time taken to be notified by IT firm and wrongly being told personal data was not put at risk